Case Studies - Greater Manchester Police

Greater Manchester Police


Project Description

    Greater Manchester Police required a new training facility. An open plan classroom area and training room were required and needed to be installed within a quick timescale. Space restrictions resulted in a two storey building being used. Both floors have open plan layouts, which have been tailored to meet the clients specifications and requirements. The building is hired giving Greater Manchester police a flexible short to medium term solution.

    • Size – 115 sqm
    • Scope of Works –
      • Detailed design
      • Bespoke refurbishment
      • Delivery and installation
    • Timescales – 10 weeks
    • Build Method – Recycled steel frame modular construction